Order Building Start Date Work Completed Date Status
1 801 Mass Ave (CT) 11/15/23 11/27/23 100%
2 610 Albany St. 1/1/24 1/8/24 100%
3 750 Albany St. Power Plant 1/9/24 1/11/24 100%
4 710 Albany St. 1/9/24 1/11/24 100%
5 65 East Newton St.(D) 1/1/24 1/8/24 100%
6 85 East Concord St. 1/10/24 1/11/24 100%
7 609 Albany St. (J) 1/11/24 90%
8 85 East Newton St. (M) 1/10/24 2/5/24 100%
9 80 East Concord St. (A) 1/10/24 1/17/24 100%
10 670 Albany St. 2/1/24 2/28/24 100%
11 750 Harrison Ave. (B) 1/17/24 3/28/24 100%
12 71 East Concord St. (K) 1/26/24 2/28/24 100%
13 715 Albany St. (T) 1/26/24 3/28/24 100%
14 560 Harrison Ave. 1/10/24 4/17/24 100%
15 780 Harrison Ave 2/2/24 2/14/24 100%
16 650 Albany St. (X) 1/16/24 2/29/24 100%
17 700 Albany St. (W) 1/17/24 2/14/24 100%
18 75 East Newton St. (E) 1/22/24 2/28/24 100%
19 72 East Concord St. (L) 1/30/24 4/17/24 100%
20 815 Albany St. (MSR) 1/11/24 3/11/24 100%
21 100 East Newton St. (G) 12/15/23 30%
22 620 Albany St. (NEIDL) 3/28/24 10%