March 2011

March 2011: Construction Update

Updates captured in photos include:

  • Forms for foundation wall being constructed
  • Wall footing being set in place
  • Sewer injector pit under construction
  • The irrigation pit being back filled over
  • Concrete has started to be poured for foundation walls
  • Underground drainage system to start soon
  • 90% of footing is complete
  • Concrete wall has been placed on Albany street side
  • Underground plumbing - perimeter drains to begin soon
  • April 15th the steel work will begin

  • 2011-03-08_09-12-37_940 2011-03-08_09-12-43_596 2011-03-08_09-12-50_869 2011-03-08_11-48-14_198 2011-03-08_11-48-28_375 2011-03-08_11-49-00_728 2011-03-08_11-49-25_266 2011-03-15_10-03-12_880 2011-03-15_10-03-20_169 2011-03-15_10-03-33_931 2011-03-17_11-25-51_114 2011-03-17_11-25-55_995 2011-03-17_11-30-08_853